heat exchanger tube bundle replacement service

Heat exchanger tube bundle replacement service: when retubing beats a new shell

A heat exchanger tube bundle replacement service exists because the shell of a shell and tube unit usually outlives its tubes by a wide margin. The pressure boundary — shell, flanges, nozzles — is thick-walled and carries a corrosion allowance measured in millimetres. The tubes are thin-walled by necessity, because heat has to pass through the wall, and they are the first thing to fail. Replacing the bundle reuses the most expensive and least worn part of the unit.

The decision is not sentimental about the existing equipment. Retubing is worth doing when the shell and tubesheet are sound and the process duty has not changed; it is a waste of money when the shell is pitted through, the tubesheet ligaments are gone, or the unit was undersized from the day it was installed.

What the service covers, stage by stage

A bundle replacement is a sequence of inspections as much as a sequence of operations, and each stage can end the job.

  • Isolation and opening. Drain, depressurise, disconnect piping, remove the channel or bonnet and the rear head. Bolting is often the first problem: corroded studs on a unit that has not been opened in years consume a full shift.
  • Bundle extraction. Pull the bundle horizontally or vertically depending on the layout, with a sling on the bundle shell and a spreader so the tubes are not bent on the way out. A bundle that will not move is usually held by scale between the baffles and the shell, not by the tubesheet.
  • Condition assessment. Measure shell wall thickness by ultrasonic scanning at the inlet impingement zone and at the liquid line; check the tubesheet for ligament cracking and corrosion between tubes; check baffle thickness and tie rods.
  • Re-tubing. Remove the old tubes — cut at the tubesheet face and pull, or drill out the stubs — clean and inspect the holes, then fit new tubes and make the joints.
  • Rebuild and test. New gaskets, new bolting where the old is suspect, bundle reinsertion, hydro test, and a drying and preservation routine before the unit goes back into service.

Every one of those stages has a decision in it that belongs to the owner, not the workshop. The workshop can tell you the shell is thin; only the owner can decide whether thin is acceptable for another five years of the same duty.

Measurements that decide whether retubing is possible

Retubing is a dimensional exercise before it is a welding exercise. The new bundle has to match the old one closely enough to enter the shell and seat in the tubesheet, and the data needed to guarantee that is rarely on the nameplate.

  • Shell inside diameter, measured in two planes and at both ends; an out-of-round shell will pinch a new bundle.
  • Bundle outside diameter at the baffles, and the baffle outside diameter against the shell bore, because that diametral clearance sets both the bypass leakage and the ease of insertion.
  • Tube outside diameter, wall thickness and length. Wall thickness is frequently quoted in Birmingham Wire Gauge rather than millimetres, and the two are not interchangeable at the drawing stage.
  • Tube count, pitch and layout angle, usually 30, 60 or 90 degrees; layout angle changes the tube count for the same shell and cannot be substituted casually.
  • Tubesheet thickness and the ligament width between holes. A tubesheet with wasted ligaments cannot be re-tubed safely whatever the tubes look like.
  • Baffle spacing, baffle cut and number of passes, which together define the thermal performance the replacement has to reproduce.

Send us the fluid on each side, the flow rate, the inlet and outlet temperature on both sides, and the heat duty; add the design pressure and temperature and the tube and shell materials if they are fixed. What comes back is a sized quotation setting out the proposed surface area, tube count and layout, and the pressure drop on each side, so the unit can be checked against the duty before anything is ordered. If you want to bound the duty yourself first, the sizing and selection tools will produce the numbers we work from.

Tube-to-tubesheet joints: expanded, seal welded or strength welded

The joint is where most retubed bundles fail, and the choice of joint type is a process decision as much as a mechanical one.

Expanded joints roll the tube into the hole, with one or two grooves in the hole taking the material. They are the default for moderate pressure and temperature, they can be re-rolled after a leak, and they are the easiest to make well. Their weakness is that they relax under thermal cycling, and they do not tolerate a tubesheet hole that has been enlarged by corrosion.

Seal welded joints add a light weld at the tube end purely to stop crevice corrosion between tube and hole. The weld carries no structural load; the roll still does the sealing. This is the usual answer for stainless and duplex tubes in chloride-bearing water, where the crevice is the failure site rather than the tube wall.

Strength welded joints carry the load in the weld and are used where the roll alone cannot be trusted: high pressure, severe thermal cycling, titanium tubes, or a tubesheet that cannot be grooved. They cost more per joint and are much harder to repair in the field, so they are specified deliberately rather than by default.

Whichever is used, the qualification of the joint procedure and the operator matters more than the joint type on the drawing. A rolled joint made with the wrong expansion pressure is either under-expanded and leaks at once, or over-expanded and thins the tube wall until it cracks a month later.

Tube material and wall thickness for the duty

The tube is the only part of the exchanger that has to be thin and corrosion resistant at the same time, which is why material selection dominates bundle life.

  • Carbon steel for clean cooling water and non-aggressive process streams, with a corrosion allowance and a realistic expectation of a shorter life than the shell.
  • 304 and 316L stainless for general process duty. 316L is the default where chlorides are present at low concentration, but austenitic stainless is vulnerable to chloride stress corrosion cracking above roughly 60 degrees Celsius in the presence of chlorides, and that limit is a design constraint, not a suggestion.
  • Duplex stainless where chloride stress corrosion cracking and erosion-corrosion both have to be resisted, at higher strength and higher cost.
  • Titanium for seawater and heavily chlorinated cooling water, where nothing else survives the life of the plant.
  • Copper alloys for clean water duties where thermal conductivity matters more than corrosion margin, provided the water chemistry suits them.

Wall thickness is chosen from a corrosion allowance plus a structural minimum, and the temptation is always to specify thinner to improve heat transfer. The gain is small — a thinner wall buys a few percent of overall coefficient — while the loss in corrosion margin is measured in years.

The four ways a bundle fails

Understanding the failure mechanism is what stops the replacement bundle failing the same way.

  • General wall loss. Uniform thinning across the tube, visible on the outside of the bundle as a change in colour and texture. Usually a water chemistry problem on the cooling side.
  • Pitting under deposits. Localised deep pits under scale or biofilm, often on the water side at low-velocity zones. The tube looks sound until it perforates.
  • Erosion-corrosion at the inlet. The first few hundred millimetres behind the inlet nozzle lose wall from turbulence and entrained solids. An impingement plate is the cheap fix and is often omitted.
  • Vibration fatigue. Tubes crack where they pass through baffle holes or at the tubesheet, from cross-flow-induced vibration. The crack is circumferential and clean, and the fix is baffle spacing or support, not a thicker tube.

Crevice corrosion at the tube-to-tubesheet joint deserves separate mention because it looks like a tube failure and is not: the tube is sound everywhere except in the half millimetre where it meets the hole.

Hydro testing and inspection after retubing

A retubed bundle is proved by test, not by inspection. The shell side is hydro tested in accordance with the applicable code, and the tube side is tested separately so that a leak can be attributed to one side.

Under ASME Section VIII Div 1, the hydrostatic test pressure for a vessel is set at 1.3 times the maximum allowable working pressure, adjusted for the ratio of allowable stress at test temperature to allowable stress at design temperature (UG-99). Testing at a lower pressure because the piping cannot take it requires a documented alternative, not an improvised one.

For the bundle itself, three checks matter beyond the pressure test: a tube-to-tube leak check with the shell side filled and the tube side open, a helium or tracer test where the duty is hazardous, and a visual inspection of every visible tube end after the first thermal cycle. The joint that weeps is nearly always found in the first week, and it is much cheaper to find it before the unit is insulated and the scaffolding struck.

Turnaround planning: the items that delay a retube

Most retubing jobs that overrun do so for reasons that had nothing to do with tubes.

  • Gaskets and bolting. Spiral wound gaskets in the correct material and studs in the correct grade are long-lead items on an old unit and are routinely forgotten.
  • Lifting and access. A bundle is heavy and awkward, and the space in front of the channel has to be clear before the job starts, not when the crane arrives.
  • Dimensional surprises. A bundle that was re-tubed once before by another workshop may not match the original drawing. Measure before the new bundle is fabricated.
  • Disposal. Old bundles are contaminated waste and need a route off site.

Retube or replace: the decision rules

The comparison is not the price of a bundle against the price of an exchanger. It is the cost per year of remaining life on each option, and four facts decide it.

  • Shell condition. If ultrasonic thickness survey shows the shell at or below the minimum required thickness, no bundle saves the unit.
  • Tubesheet condition. Wasted ligaments, cracked holes or a corroded face mean the tubesheet has to be replaced, which changes the scope from retubing to remanufacture.
  • Duty change. A unit that was undersized, or that now has to handle a higher flow, is not worth retubing to the old geometry.
  • Availability. A retube keeps the existing nozzles, foundation and piping; a new unit may require all three to change.

What to put in the enquiry for a tube bundle replacement service

A quotation for a tube bundle replacement service cannot be accurate without the geometry and the duty, and a workshop that quotes from a model number is quoting a guess.

ItemWhat to send
DrawingsGeneral arrangement, tubesheet layout, baffle arrangement; a scan of the original is enough
NameplatePhotograph, including design pressure, temperature, and code stamp details
Measured geometryShell ID, bundle OD, tube OD and wall, tube length, tube count and pitch
MaterialsCurrent tube, shell and tubesheet materials, and what the duty actually requires
DutyFluids, flow rates, inlet and outlet temperatures, heat duty, allowable pressure drop
ConditionPhotographs of the failed tubes, the tubesheet face and the shell bore
ConstraintsShutdown window, lifting access, and whether the shell can be re-used

Working with a tube bundle replacement service across borders

For an owner importing a replacement bundle, three things decide whether it fits on arrival. The drawings have to be the drawings for that unit and not for a similar one. The dimensional report has to be issued against measured values rather than nominal ones, because a thirty-year-old shell is rarely at nominal. And the inspection documents — material certificates, joint procedure qualification, test reports — have to travel with the bundle, because a bundle that arrives without them cannot be accepted into a coded system without re-testing.

The shell and tube heat exchanger range covers new bundles and complete units where the shell has gone too far, and the wider heat exchanger services page sets out the design-to-commissioning scope. If the question is whether the existing unit can be saved at all, that is worth settling before a bundle is ordered — and it is settled with thickness readings and a tubesheet inspection, not with an opinion.

For anything time-critical, send the drawings and the measured geometry through the contact page and mark what the shutdown window is. The engineering answer and the schedule answer are usually decided together.